Policy & Legal Framework
Central Policy & Auctions
National plans and roadmaps together with auction schedules, price ceilings and evaluation guidelines.
How projects are selected
A licence does not bring revenue. Offshore wind projects reach a bankable position by winning a fixed price competitive auction that carries a 20 year offtake, run by the Korea Energy Agency under the Renewable Portfolio Standard. Certificates carry higher multipliers the further offshore and the deeper the site, which is how the scheme rewards the harder locations.
Under the Special Act a second track opens alongside it: operators are selected by competitive bidding within designated development zones. The two tracks now run in parallel, and which one a project sits on determines both its timetable and what it must prove.
Free account
Open the source documents
A free KWI account opens the Korean source document on every entry in this tracker.
Premium
Read it in English
Premium opens the English translation PDFs on this page, KWI Weekly, and the Legislation & Guideline Updates, Recent Regulatory Filings and Project Filings sections of the Daily newsletter.
Entries
- 2026-10-30Korea Energy AgencyH2 2026 offshore wind fixed-price competitive bidding announced(재생에너지센터 공고 제2026-36호) 2026년 하반기 해상풍력 고정가격계약 경쟁입찰 ...The Renewable Energy Center has announced a competitive bidding process for offshore wind fixed-price contracts in the second half of 2026. This procurement mechanism aims to support the development of offshore wind capacity through competitive selection.Source ↗Free membersEN translation · PDFPremium members
- 2026-10-30Korea Energy Agency2026 Alternative Compliance Auction Announced2026년 대체이행 입찰 공고The government has announced a competitive bidding process for alternative compliance obligations in 2026. This auction will determine capacity and pricing for renewable energy projects meeting regulatory requirements.Source ↗Free membersEN translation · PDFPremium members
- 2026-10-13Korea Energy AgencyKEA posts H2 2026 wind competitive bidding briefing materials, with scoring changes and schedule2026년 하반기 풍력 고정가격계약 경쟁입찰 종합설명회 발표자료 게시The Korea Energy Agency posted the presentation materials from its 13 October 2026 briefing on the second-half 2026 wind fixed-price contract competitive bidding. The materials cover the promotion plan, amendments to the scoring system for offshore wind, guidance on preparing the project details statement and the schedule, with the notice planned from the end of October 2026.Source ↗Free membersEN translation · PDFPremium members
- 2026-09-30GovernmentPublic hearing handout: draft RPS sunset and contract market subordinate statutesRPS 개편 재생에너지법 하위법령 개정안 대국민 공청회 자료집(2026. 9. 30.)Handout of the public hearing held on 30 September 2026 by the Ministry of Climate, Energy and Environment and the Korea Energy Agency on the draft amendments to the subordinate statutes of the Renewable Energy Act for the RPS overhaul: the sunset of the RPS and the introduction of the contract market system. The PDF contains the English translation followed by the 50-page Korean original.Link to be addedFree membersEN translation + KO original · PDFPremium members
- 2026-08-06Korea Energy AgencyKS certification body designation change for large wind turbines중대형 풍력터빈 KS인증 위탁기관 지정 변경사항 공고The government announced changes to the designated certification body for KS (Korean Industrial Standards) certification of large wind turbines. This administrative update affects the institutional framework for quality assurance and standards compliance in the domestic offshore wind turbine sector.Source ↗Free membersEN translation · PDFPremium members
- 2026-06-30Ministry of Climate, Energy & EnvironmentMid-to-Long-Term Offshore-Wind Bidding Roadmap해상풍력 중장기 입찰 로드맵Korea’s first ten-year (2026-2035) offshore-wind auction plan, published by the Ministry of Climate, Energy and Environment on 30 June 2026. It commits 55 GW of tenders over the decade (4 GW or more each year, against actual annual tenders of 0.55 GW in 2022 rising to 1.8 GW in the first half of 2026) with about 28 GW front-loaded into 2026-2030. It targets 10.5 GW deployed or under construction by 2030 and 25 GW of cumulative deployment by 2035. Two tracks run in parallel: the existing fixed-price competitive auctions (about 31 GW through 2033) and, from the second half of 2029, the Special Act’s development zone auctions (2 GW a year to 2030, then 4 GW a year in 2031-2035, totalling 24 GW by 2035). The government aims for at least a 2:1 effective competition ratio and will review and revise the roadmap every three years.Source ↗Free membersEN translation · PDFPremium members
- 2026-05-15Ministry of Climate, Energy & EnvironmentShared Offshore-Wind Grid Connection해상풍력 공동접속설비A May 2026 policy from the Ministry of Climate, Energy and Environment under which the state, with KEPCO, builds shared “collective substations” on islands or the coast so that several offshore-wind projects connect through one link instead of each laying its own cable to an onshore substation. Following the December 2024 offshore-wind infrastructure plan, nine candidate hubs were identified; the Haenam cluster in Jeonnam starts first under a KEPCO-developer agreement. Pooling the connections there cuts total cable length from 703 km to 287 km (a 59% reduction), saves about KRW 3.6 trillion in investment versus individual links, and lowers the generation cost by roughly 20 KRW/kWh. The government plans to extend shared connection to other dense clusters by the third quarter of 2026, with costs shared in proportion to each project developer’s capacity.Source ↗Free membersEN translation · PDFPremium members
- 2026-03-26Ministry of Climate, Energy & EnvironmentGovernment-Led Planned-Siting Regime정부주도 계획입지 제도The core shift under the Offshore Wind Special Act, in force since 26 March 2026: the government, not developers, drives siting. The Ministry of Trade, Industry and Energy and the Ministry of Oceans and Fisheries, through the Offshore Wind Power Committee, first designate “preliminary zones” where wind, environmental and community conditions are strong, then “development zones,” after which operators are selected by competitive bidding. Bundling the approvals this way is intended to cut a project’s preparation period from about ten years to five or six.Source ↗Free membersEN translation · PDFPremium members
- 2026-03-26Ministry of Climate, Energy & EnvironmentOffshore Wind Power Committee & Promotion Group해상풍력발전위원회·추진단The Offshore Wind Power Committee, chaired under the Prime Minister, is the top governance body created by the Special Act. It coordinates differences between ministries and deliberates the major decisions (including the designation of preliminary zones and development zones) supported by a dedicated inter-ministerial promotion task force.Source ↗Free membersEN translation · PDFPremium members
- 2026-03-26Ministry of Climate, Energy & EnvironmentFisheries Coexistence & Community Benefit-Sharing어업 상생·주민 이익공유The Special Act’s mechanism for community acceptance: for each preliminary zone, the local mayor or county head convenes a public-private cooperation council that brings in fishery groups, resident representatives and relevant experts to help shape the designation of development zones and the sharing of project benefits: the channel through which fisheries coexistence and community compensation are negotiated.Source ↗Free membersEN translation · PDFPremium members
- 2026-03-26Ministry of National DefenseMilitary & Airspace Coordination국방부 군사협의·항공 조정Central coordination with the Ministry of National Defense where offshore-wind sites or their radar footprint touch military protection zones: a standing consultation gate in the permitting process.Source ↗Free membersEN translation · PDFPremium members
- 2025-02-21Ministry of Trade, Industry & Energy11th Basic Plan for Electricity Supply and Demand (2024-2038)제11차 전력수급기본계획Korea's statutory 15-year power-sector roadmap under the Electric Utility Act, confirmed by MOTIE on 21 February 2025 and covering 2024-2038. It sets the capacity the offshore-wind auctions must help fill: solar and wind reach about 115.5 GW by 2038 and total renewables about 121.9 GW, lifting renewables to roughly a 33% share of generation, with about 7 GW of new renewable capacity added every year to 2030.Source ↗Free membersEN translation · PDFPremium members
- 2025-01-03Ministry of Oceans & FisheriesMarine-Use Impact Assessment System해양이용영향평가 체계The Ministry of Oceans and Fisheries’ marine-environmental review, which an offshore-wind project must clear to use the sea. A sea-area use consultation is scaled by project size up to a full impact assessment. Once part of the Marine Environment Management Act, it became a standalone law (the Marine Use Impact Assessment Act, enacted 2 January 2024 and in force from 3 January 2025) with offshore-wind-specific guidelines and a deliberation committee that fixes each project’s assessment scope in advance.Source ↗Free membersEN translation · PDFPremium members
- 2023-08-01Ministry of Trade, Industry & EnergyDetailed Criteria for Electricity Business Permits (Notice)발전사업 세부허가기준 등에 관한 고시The MOTIE notice that tightened generation-permit criteria (recognising only offshore met masts with a three-year validity, a minimum paid-in-capital test, and a five-year construction-plan period) to curb reckless applications and met-mast squatting ahead of the Special Act.Source ↗Free membersEN translation · PDFPremium members
- 2023-01-01Korea Energy AgencyOffshore-Wind Fixed-Price Competitive Bidding해상풍력 고정가격계약 경쟁입찰Korea’s primary route to market for offshore wind: an annual competitive auction, run since 2023, that awards a 20-year fixed-price contract. Bids are scored on price against a government-set ceiling and on non-price criteria such as domestic industrial contribution, safety and community acceptance. The 2026 first-half round offered about 1,800 MW (1,400 MW fixed-bottom and 400 MW floating, the first year the two ceilings were set separately) at price caps of 171.229 KRW/kWh for fixed-bottom and 175.100 KRW/kWh for floating; five projects totalling 1,786 MW were selected.Source ↗Free membersEN translation · PDFPremium members
- 2022-01-01Korea Energy AgencyPublic-Led Large-Scale Offshore-Wind Site Development Support공공주도 대규모 해상풍력 단지개발 지원사업A Korea Energy Agency programme that funds local governments to scout and verify large offshore-wind sites before developers step in: an early precursor to the Special Act’s government-led planned siting. Selected local governments receive up to KRW 6.3 billion over three years, matching at least half the cost with local funds, to run wind-resource and marine surveys, regulatory and community-acceptance checks and a master plan. Boryeong, Sinan, Taean, Gunsan and North Jeolla Province have been among the participants.Source ↗Free membersEN translation · PDFPremium members
- 2012-01-01Korea Energy AgencyRenewable Portfolio Standard (RPS) & REC Multiplier신재생에너지 공급의무화(RPS) 및 REC 가중치The Renewable Portfolio Standard, in force since 2012, requires generators above 500 MW (the state gencos and other large operators) to supply a rising share of their power from renewables (2% in 2012, climbing to 10% by 2022). Offshore wind earns Renewable Energy Certificates (RECs) with higher multipliers the farther a project sits from shore and the deeper the water; historically the main support channel, RECs are now being succeeded by the 20-year fixed-price auctions.Source ↗Free membersEN translation · PDFPremium members