Yeosu Dado #1
Jeonnam waterspublic여수 다도1 해상풍력 · db 48
FixedEBL approved · 2021-05-28
Yeosu Dado #1 is a 256 MW fixed-bottom offshore wind project in Jeonnam waters. It was first granted an Electricity Business Licence on 2021-05-28. It is one of the 3 projects in the group listed below.
Location & map
free membersKWI project map · member login required
Permits & EIA timeline
premium membersAnalysis report · Yeosu Dado #1
coming soonIn preparation
The analysis report for this project is in preparation.
Group · 3 projects
1,272 MW on recordpublic head| Project | Developer | Capacity | Status | EIA code |
|---|---|---|---|---|
| Yeosu Dado #1 · this page | Northland Power | 256 MW | EBL approved | - |
| Yeosu Dado #2 | Northland Power | 376 MW | EBL approved | - |
| Yeosu Dado #3 | Northland Power | 640 MW | EBL approved | - |
Group = projects KWI records as developed together, based on the developer and SPC on record
Source: KWI project database (Master DB) and Data Hub filings · as of 2026-10-08