Permits & Licensing · Stage 2 · Electricity Business License (EBL)

Electricity Business License (EBL)

발전사업허가(EBL)

Category
Permits & Licensing · Stage 2 · Electricity Business License (EBL)
Responsible body
Ministry of Climate, Energy & Environment (after Electricity Regulatory Commission deliberation) or Mayor/Do Governor
Governing law
Electric Utility Act
Korean original
National Law Information Center (law.go.kr) ↗

Summary

Public

The foundational licence for pursuing generation-business development at the project site, tracked as the anchor permit in KWI's project pipeline. The license must be obtained from the Minister of Climate, Energy and Environment or the competent Mayor/Do Governor, and the Minister must first undergo deliberation of the Electricity Regulatory Commission. Criteria include financial and technological means, the ability to perform it as planned and, for wind power, gathering residents' opinions through advance notice. Installations must be set up and business commenced within the period for preparation, which may not exceed the period the Minister sets within 10 years unless the permitting authority extends it for just grounds. The license must be revoked if this is not done, or if works cannot commence because construction plan authorization was not obtained, without just ground, by the publicly notified time.

Sources: Electric Utility Act, Article 7, Article 9, Article 12.

Legal basis

Electric Utility Act

Article 7 (Electric utility licenses)

제7조(전기사업의 허가)

KWI translation. The Korean text of this Article changed after the official English translation; KWI amended the official English to match.

(1) A person who intends to operate the electric utility business shall obtain a license by type or scale of the electric utility business from the Minister of Climate, Energy and Environment or the competent Mayor/Do Governor (hereinafter referred to as "permitting authority"), as prescribed by Presidential Decree. The same shall also apply to any modification to important matters prescribed by Decree of the Ministry of Climate, Energy and Environment from among permitted matters.

Further text omitted.

Excerpt: paragraph (1) of each article. English text: Official KLRI English, updated by KWI. The full articles are in the English translation of the governing law below.

Where it sits in the permit pathway

Stage 2 of 7
  1. 1Wind Measurement2 authorizations
  2. 2Electricity Business License (EBL)1 authorization
  3. 3Environmental Assessment2 authorizations
  4. 4Site Investigation2 authorizations
  5. 5Public-Waters Use & Navigation Safety2 authorizations
  6. 6Cross-sector Consents5 authorizations
  7. 7Construction & Operation2 authorizations

Stages where risk concentrates. See the full permit pathway ›

Related entries in this tracker

Public-Waters Occupancy Permit: Met MastStage 1
Met-Mast Rules & 3-Year ValidityStage 1
Environmental Impact AssessmentStage 3
Marine Use Consultation & Impact AssessmentStage 3
Implementation-plan approval under the Special Act (one-stop)Special Act
The full permit pathwayPermits & Licensing

English translation of the governing law Premium members

Download English translation (unofficial) · PDF

KWI_EN_Electric-Utility-Act_20260918_KLRI-KWI.pdf · 108 pages
Based on the official KLRI English text, checked and updated by KWI against the Korean text in force on 18 September 2026

Korean original ↗

English translations are provided for convenience. They are unofficial; the Korean original is authoritative.