Permits & Licensing · Stage 1 · Wind Measurement

Met-Mast Rules & 3-Year Validity

계측기 규정 및 3년 유효기간

Category
Permits & Licensing · Stage 1 · Wind Measurement
Responsible body
Ministry of Climate, Energy & Environment / Korea Energy Agency
Governing law
Notice on Detailed Criteria for Electricity Business Permits
Korean original
National Law Information Center (law.go.kr) ↗

Summary

Public

Since August 2023 this Notice recognises only offshore (not onshore) met masts for offshore-wind permits and sets a three-year validity: the developer must apply for the Electricity Business License within three years of the met-mast permit. Introduced with tighter capital and construction-period rules to curb reckless applications and met-mast squatting ahead of the Special Act's planned-siting regime, it was followed by the Special Act's bar on new met-mast public-waters permits outside planned zones. Attached Table 2 requires measurement data for 365 days or more with availability of 90% or more, except for small wind power, and sets an offshore device's effective area as the sea area within a 7 km radius. Where effective areas overlap, priority follows installation permit dates, but an offshore device not installed within 12 months is excluded from priority, with periods of unavoidable causes not counted.

Sources: Notice on Detailed Criteria for Electricity Business Permits, Attached Table 2.

Legal basis

Notice on Detailed Criteria for Electricity Business Permits

Attached Table 2 of the Notice sets the criteria for wind resource measurement and for overlapping wind power sites, applicable from 1 August 2023 (Article 39, item 2).

Where it sits in the permit pathway

Stage 1 of 7
  1. 1Wind Measurement2 authorizations
  2. 2Electricity Business License (EBL)1 authorization
  3. 3Environmental Assessment2 authorizations
  4. 4Site Investigation2 authorizations
  5. 5Public-Waters Use & Navigation Safety2 authorizations
  6. 6Cross-sector Consents5 authorizations
  7. 7Construction & Operation2 authorizations

Stages where risk concentrates. See the full permit pathway ›

Related entries in this tracker

Public-Waters Occupancy Permit: Met MastStage 1
Electricity Business License (EBL)Stage 2
Implementation-plan approval under the Special Act (one-stop)Special Act
The full permit pathwayPermits & Licensing

English translation of the governing law Premium members

Download English translation (unofficial) · PDF

KWI_EN_Electricity-Generation-License-Criteria-Notice_20251224_v1.0.pdf · 41 pages
Translated from the Korean text in force on 24 December 2025

Korean original ↗

English translations are provided for convenience. They are unofficial; the Korean original is authoritative.