Permits & Licensing · Stage 5 · Public-Waters Use & Navigation Safety
Maritime Traffic Safety Audit
해상교통안전진단
Summary
PublicAssessment of the wind farm's impact on vessel navigation and maritime traffic safety. Under the Act, the Minister of Oceans and Fisheries must require a business entity intending to carry out a project subject to safety examination to conduct a marine traffic safety examination. When seeking permission, etc. under statutes such as the Public Waters Management and Reclamation Act, the entity submits the safety examination report to the disposing authority, which must forward it to the Minister within 10 days, before granting it. The Minister must notify a review opinion within 45 days, not counting time for supplementing documents or consulting relevant agencies. The disposing authority must grant permission, etc. by reflecting the review opinion or review results, and must order project suspension where a compliance order is not followed and marine traffic safety would be significantly affected.
Sources: Maritime Traffic Safety Act, Article 13, Article 16.
Legal basis
Maritime Traffic Safety ActArticle 13 (Marine traffic safety examinations)
제13조(해상교통안전진단)
(1) The Minister of Oceans and Fisheries shall require a person who intends to carry out a project subject to safety examination (excluding the head of a State organ or the head of a local government; hereinafter referred to as "business entity") to conduct a marine traffic safety examination in accordance with the safety examination standards prescribed by Decree of the Ministry of Oceans and Fisheries.
Further text omitted.
Article 16 (Permission by disposing authorities)
제16조(처분기관의 허가 등)
(1) A disposing authority shall grant permission, etc. by reflecting a review opinion against which no objection has been filed or review results, and shall notify the Minister of Oceans and Fisheries when it has granted permission, etc.
Further text omitted.
Excerpt: paragraph (1) of each article. English text: KWI translation. The full articles are in the English translation of the governing law below.
Where it sits in the permit pathway
Stage 5 of 7- 1Wind Measurement2 authorizations
- 2Electricity Business License (EBL)1 authorization
- 3Environmental Assessment2 authorizations
- 4Site Investigation2 authorizations
- 5Public-Waters Use & Navigation Safety2 authorizations
- 6Cross-sector Consents5 authorizations
- 7Construction & Operation2 authorizations
Stages where risk concentrates. See the full permit pathway ›
Related entries in this tracker
| Geotechnical Survey (GT): Occupancy & Work Plan | Stage 4 |
| Geophysical Survey (GP) | Stage 4 |
| Public-Waters Occupancy Permit: Project | Stage 5 |
| Development-Activity Permit | Stage 6 |
| Military Installations Consultation | Stage 6 |
| Radio-Station Permit | Stage 6 |
| National Heritage Impact Diagnosis | Stage 6 |
| Forest & Farmland Conversion | Stage 6 |
| Implementation-plan approval under the Special Act (one-stop) | Special Act |
| The full permit pathway | Permits & Licensing |
English translation of the governing law Premium members
Download English translation (unofficial) · PDFKWI_EN_Sea-Traffic-Safety-Act_20240126_v1.0.pdf · 105 pages
Translated from the Korean text in force on 26 January 2024
English translations are provided for convenience. They are unofficial; the Korean original is authoritative.