Summary

Public

Assessment of the wind farm's impact on vessel navigation and maritime traffic safety. Under the Act, the Minister of Oceans and Fisheries must require a business entity intending to carry out a project subject to safety examination to conduct a marine traffic safety examination. When seeking permission, etc. under statutes such as the Public Waters Management and Reclamation Act, the entity submits the safety examination report to the disposing authority, which must forward it to the Minister within 10 days, before granting it. The Minister must notify a review opinion within 45 days, not counting time for supplementing documents or consulting relevant agencies. The disposing authority must grant permission, etc. by reflecting the review opinion or review results, and must order project suspension where a compliance order is not followed and marine traffic safety would be significantly affected.

Sources: Maritime Traffic Safety Act, Article 13, Article 16.

Legal basis

Maritime Traffic Safety Act

Article 13 (Marine traffic safety examinations)

제13조(해상교통안전진단)

(1) The Minister of Oceans and Fisheries shall require a person who intends to carry out a project subject to safety examination (excluding the head of a State organ or the head of a local government; hereinafter referred to as "business entity") to conduct a marine traffic safety examination in accordance with the safety examination standards prescribed by Decree of the Ministry of Oceans and Fisheries.

Further text omitted.

Article 16 (Permission by disposing authorities)

제16조(처분기관의 허가 등)

(1) A disposing authority shall grant permission, etc. by reflecting a review opinion against which no objection has been filed or review results, and shall notify the Minister of Oceans and Fisheries when it has granted permission, etc.

Further text omitted.

Excerpt: paragraph (1) of each article. English text: KWI translation. The full articles are in the English translation of the governing law below.

Where it sits in the permit pathway

Stage 5 of 7
  1. 1Wind Measurement2 authorizations
  2. 2Electricity Business License (EBL)1 authorization
  3. 3Environmental Assessment2 authorizations
  4. 4Site Investigation2 authorizations
  5. 5Public-Waters Use & Navigation Safety2 authorizations
  6. 6Cross-sector Consents5 authorizations
  7. 7Construction & Operation2 authorizations

Stages where risk concentrates. See the full permit pathway ›

Related entries in this tracker

Geotechnical Survey (GT): Occupancy & Work PlanStage 4
Geophysical Survey (GP)Stage 4
Public-Waters Occupancy Permit: ProjectStage 5
Development-Activity PermitStage 6
Military Installations ConsultationStage 6
Radio-Station PermitStage 6
National Heritage Impact DiagnosisStage 6
Forest & Farmland ConversionStage 6
Implementation-plan approval under the Special Act (one-stop)Special Act
The full permit pathwayPermits & Licensing

English translation of the governing law Premium members

Download English translation (unofficial) · PDF

KWI_EN_Sea-Traffic-Safety-Act_20240126_v1.0.pdf · 105 pages
Translated from the Korean text in force on 26 January 2024

Korean original ↗

English translations are provided for convenience. They are unofficial; the Korean original is authoritative.