Permits & Licensing · Stage 7 · Construction & Operation
Construction-Plan Authorization
공사계획 인가
Summary
PublicAuthorization of the construction plan before building the generation and transmission facilities. Under the Act, an electric utility business entity that intends to perform works determined by Decree of the Ministry of Climate, Energy and Environment for establishing or altering electric installations must obtain authorization for its plan for the works from the Minister of Climate, Energy and Environment, including for modifications. Insignificant modifications are reported to the Minister, and other works prescribed by that Decree are reported to the permitting authority before they begin. Where installations are destroyed or damaged by an accident or disaster, or in emergencies such as war, works may begin first and be reported without delay. The license must be revoked where works are not commenced because authorization was not obtained, without just ground, by the time the Minister publicly notifies.
Sources: Electric Utility Act, Article 61, Article 12.
Legal basis
Electric Utility ActArticle 61 (Authorization or reporting of plans for works for establishing electric installations for electric utility business)
제61조(전기사업용전기설비의 공사계획의 인가 또는 신고)
(1) If an electric utility business entity intends to perform works determined by Decree of the Ministry of Climate, Energy and Environment for establishing or altering electric installations for electric utility business, he or she shall obtain authorization for his or her plan for the works from the Minister of Climate, Energy and Environment. The same shall apply to any modification of authorized matters.
Further text omitted.
Excerpt: paragraph (1) of each article. English text: Official KLRI English, updated by KWI. The full articles are in the English translation of the governing law below.
Where it sits in the permit pathway
Stage 7 of 7- 1Wind Measurement2 authorizations
- 2Electricity Business License (EBL)1 authorization
- 3Environmental Assessment2 authorizations
- 4Site Investigation2 authorizations
- 5Public-Waters Use & Navigation Safety2 authorizations
- 6Cross-sector Consents5 authorizations
- 7Construction & Operation2 authorizations
Stages where risk concentrates. See the full permit pathway ›
Related entries in this tracker
| Development-Activity Permit | Stage 6 |
| Military Installations Consultation | Stage 6 |
| Radio-Station Permit | Stage 6 |
| National Heritage Impact Diagnosis | Stage 6 |
| Forest & Farmland Conversion | Stage 6 |
| Pre-Use Inspection | Stage 7 |
| Implementation-plan approval under the Special Act (one-stop) | Special Act |
| The full permit pathway | Permits & Licensing |
English translation of the governing law Premium members
Download English translation (unofficial) · PDFKWI_EN_Electric-Utility-Act_20260918_KLRI-KWI.pdf · 108 pages
Based on the official KLRI English text, checked and updated by KWI against the Korean text in force on 18 September 2026
English translations are provided for convenience. They are unofficial; the Korean original is authoritative.