Permits & Licensing · Stage 7 · Construction & Operation

Pre-Use Inspection

사용 전 검사

Category
Permits & Licensing · Stage 7 · Construction & Operation
Responsible body
Permitting authority (inspection entrusted to Korea Electrical Safety Corporation)
Governing law
Electric Utility Act
Korean original
National Law Information Center (law.go.kr) ↗

Summary

Public

Inspection certifying the completed facilities are safe to operate, the final gate before commercial operation (COD). Under the Act, a person who has completed works for establishing or altering electric installations under the construction-plan provisions may use them only after they pass an inspection conducted by the permitting authority. This inspection, and permission for temporary use, may be partially entrusted to the Korea Electrical Safety Corporation as prescribed by Presidential Decree, and an applicant pays a fee under the Electrical Safety Management Act. Where installations fail but have no defect in safe operation and temporary use is necessary, the permitting authority may permit temporary use, specifying the period and method, with the period not exceeding one year. Using installations without passing the inspection, other than under notified temporary use, is punishable by a fine not exceeding three million won.

Sources: Electric Utility Act, Article 63, Article 64, Article 97, Article 98, Article 105.

Legal basis

Electric Utility Act

Article 63 (Pre-use inspection)

제63조(사용전검사)

When a person has completed works for establishing or altering electric installations in accordance with Article 61, the person shall use these installations only after they have passed an inspection conducted by the permitting authority, as prescribed by Decree of the Ministry of Climate, Energy and Environment.

Excerpt: paragraph (1) of each article. English text: Official KLRI English, updated by KWI. The full articles are in the English translation of the governing law below.

Where it sits in the permit pathway

Stage 7 of 7
  1. 1Wind Measurement2 authorizations
  2. 2Electricity Business License (EBL)1 authorization
  3. 3Environmental Assessment2 authorizations
  4. 4Site Investigation2 authorizations
  5. 5Public-Waters Use & Navigation Safety2 authorizations
  6. 6Cross-sector Consents5 authorizations
  7. 7Construction & Operation2 authorizations

Stages where risk concentrates. See the full permit pathway ›

Related entries in this tracker

Development-Activity PermitStage 6
Military Installations ConsultationStage 6
Radio-Station PermitStage 6
National Heritage Impact DiagnosisStage 6
Forest & Farmland ConversionStage 6
Construction-Plan AuthorizationStage 7
Implementation-plan approval under the Special Act (one-stop)Special Act
The full permit pathwayPermits & Licensing

English translation of the governing law Premium members

Download English translation (unofficial) · PDF

KWI_EN_Electric-Utility-Act_20260918_KLRI-KWI.pdf · 108 pages
Based on the official KLRI English text, checked and updated by KWI against the Korean text in force on 18 September 2026

Korean original ↗

English translations are provided for convenience. They are unofficial; the Korean original is authoritative.